Back to 35 MW Package

Normal Shutdown

0%

Normal shutdown & 4-hr lockout

Step 1 of 3

Initiate Normal Stop

Controlled shutdown from the HMI. Refer to OEM manual and site procedures.

HMI Reference
action

Gradually reduce load per site guidelines.

action

Confirm all personnel and downstream systems are aware.

action

Select STOP on the Turbine Start/Stop screen.

action

Verify 52G breaker opens. Ensure 480 V supply is NOT interrupted (must transfer within 20 sec or unit enters Emergency Stop).

0/4 items checked