Back to 34 MW Package

34 MW Pre-Start

0%

Pre-power & auxiliary system checks

Step 1 of 4

Step 1 – Unit Walk-Around

Confirm the unit is site-ready, all trailers coupled and cables routed before power-on.

action

Confirm all four trailers are properly positioned and coupled: T1 (Main), T2 (Inlet), T3 (Exhaust), T4 (Distribution).

action

Verify MV cables (GEN-0071/72/81/82/91/92) are routed and connected between T1 and T4.

action

Confirm low-voltage and control cables between T1 and T4 are connected: BSDG series, TCP, DCP lines.

action

Verify grounding: all equipment grounded, grounding resistance ≤4Ω, 250MCM ground wire to main grid.

monitor

No visible leaks — fuel gas, lube oil, coolant.

0/5 items checked