SMT130 Crank Test
0%Crank test / purge (no ignition)
Step 1 of 3
Step 1 – Pre-conditions for Crank Test
Crank test is done without ignition to verify the start system and purge the exhaust. It requires EMERGENCY AC available (diesel-generator running).
monitor
Confirm the turbine is in [Ready] state on the TCP (Turbine Control Panel).
monitor
Confirm the off-skid emergency diesel-generator is running and EMERGENCY AC is available.
monitor
120 VDC battery breaker (FB1) closed. Control system energized.
monitor
Pre/post lube oil pump running. Lube oil pressure normal.
action
Gas fuel valve (FSV) CLOSED — crank with no ignition.
action
Exhaust cover and drain caps open. Area clear.
action
Verify there are no active shutdown alarms in the Alarm Bar.
0/7 items checked