Back to 6.4 MW Package
SMT60 Crank Test
0%Crank test / purge (no ignition)
Step 1 of 3
Step 1 – Pre-conditions for Crank Test
Crank test (purge crank) is performed with no ignition to verify the start system, purge the exhaust, and perform on-crank water wash. All CRANK permissives must be active.
monitor
Confirm the turbine is in [Ready] state on the TT4000 screen.
action
Verify there are NO active shutdown alarms. Correct any indication before proceeding.
monitor
Confirm pre/post lube oil pump is running and lube oil pressure is normal.
action
Confirm the gas fuel valve (FSV) is CLOSED for crank with no ignition.
action
Exhaust cover removed. Exhaust area clear of personnel.
action
Notify supervisor and area personnel that a crank test will be performed.
0/6 items checked