Back to 6.4 MW Package

SMT60 Crank Test

0%

Crank test / purge (no ignition)

Step 1 of 3

Step 1 – Pre-conditions for Crank Test

Crank test (purge crank) is performed with no ignition to verify the start system, purge the exhaust, and perform on-crank water wash. All CRANK permissives must be active.

monitor

Confirm the turbine is in [Ready] state on the TT4000 screen.

action

Verify there are NO active shutdown alarms. Correct any indication before proceeding.

monitor

Confirm pre/post lube oil pump is running and lube oil pressure is normal.

action

Confirm the gas fuel valve (FSV) is CLOSED for crank with no ignition.

action

Exhaust cover removed. Exhaust area clear of personnel.

action

Notify supervisor and area personnel that a crank test will be performed.

0/6 items checked