Step 1 of 8

Step 1 – Glycol level check

PLUM Gas Solutions · Unit 351-PRS. Ensure expansion chamber sight glass shows sufficient glycol before any burner operation. Field equipment reference.

Field equipment reference
action

Perform visual check of glycol level on the expansion chamber.

monitor

Ensure level is at least two (2) inches above the bottom of the sight glass.

action

If level is low, do not proceed — top up glycol per site procedure.

0/3 items checked