Back to Trailered Pressure Regulation System

PRS Startup
0%PRS valve sequence & glycol bath
Step 1 of 4
Phase 1 – Pre-Startup Checks
PRS startup sequence summary. Refer to OEM manual and site procedures for full steps.
Contact OEM or qualified technical support before adjusting any regulator settings.
action
Verify no ignition sources in the vicinity.
monitor
No open flames, sparks, or running vehicles within 15 feet.
action
Verify glycol fluid level in the bath is at least 2 inches above the bottom of the sight glass.
monitor
Glycol level visible and within specification.
action
Verify all connections — both upstream and downstream of the PRS — are in place, secure, and pressure-tight.
action
Verify pipe supports are in place (if required).